BUILDING REPAIR UPDATE - 7/11/08

  1. The chimney and fireplace have been removed.
  2. The repairs to the north and south walls are complete.
  3. Sheer walls have been put in place in the north and south ends of the Fellowship Hall.
  4. Blocking is being added to all of the sanctuary perimeter walls.
  5. Pending projects include:
  • Adding blocking between the top plate and the roof so that a positive connection can be made and the roof can be secured to the top plate.
  • Installing the ridge beam inside the sanctuary at the peak of the ceiling.
  • Removal of additional siding.
  • Install blocking in the sanctuary floor system.